Expert witness fees and timescales in building disputes
The question we are asked most often by homeowners, contractors and their solicitors is how much an expert report will cost and how long it will take. The honest answer is that it depends on the issues, the documents and the stage of the dispute. Here is what drives the cost and timescale, and how to keep both proportionate.
How experts charge
Most construction and surveying experts charge on a time basis, at an hourly or daily rate that reflects the expert's seniority, plus expenses such as travel. A good expert will not give a meaningful estimate until they understand the case. The RICS standard Surveyors acting as expert witnesses requires the scope of the appointment and the basis of the fees to be confirmed in writing before the work starts.
In practice, that usually means:
- A short initial review, sometimes free or for a modest agreed charge, to read the key documents, check for conflicts and confirm whether the matter is within the expert's expertise.
- A written estimate for each stage: inspection, analysis, the report, responding to written questions, an experts' meeting and joint statement, and attendance at a hearing.
- Clear terms on cancellation, particularly for hearing dates, because experts reserve time that cannot easily be re-let.
Where both parties instruct a single joint expert, the fee is normally shared equally unless the court orders otherwise, and both parties are jointly and severally liable for it.
Why experts cannot work on a success fee
The independence of expert evidence depends on the expert having no stake in the outcome. The RICS standard prohibits surveyors from accepting expert witness instructions where their fee depends on the outcome of the case, apart from a narrow exception with strict conditions. If someone offers expert evidence on a no-win, no-fee basis, it is worth asking how the evidence will stand up to that point being raised.
What drives the cost
- The number and type of issues. A single question about whether a roof was defective and what it costs to repair is very different from a final account with fifty disputed variations, delay and defects.
- The records. Well-organised contracts, drawings, valuations, instructions and photographs keep costs down. Gaps mean more time reconstructing what happened.
- Site inspection and opening-up. Defects often cannot be diagnosed without removing finishes or testing. That needs access, a contractor and sometimes the other side's agreement.
- Measurement and costing. A properly measured and priced remedial scope takes longer than adopting a contractor's quotation, but it is far more persuasive.
- Other experts. Many building disputes need more than one discipline, for example a structural engineer alongside the quantity surveyor. Coordinating the scope avoids paying twice.
- The procedural stage. A preliminary advisory report before proceedings is quicker and cheaper than a full Part 35 report with a joint statement and trial attendance.
Typical timescales
These are general indications, not promises, and they depend on access and documents:
- Initial review and conflict check: usually within a few working days of receiving the documents.
- Site inspection: arranged around access, often within two to three weeks.
- Report: for a straightforward residential defects or cost matter, commonly four to eight weeks from receiving full instructions and documents. Complex quantum disputes take longer.
- Written questions: the CPR timetable allows 28 days for questions to be put. Answers are normally given within the period set by the court or agreed.
If there is a court deadline, tell the expert at the outset. A good expert will tell you early if a deadline is at risk, rather than at the last minute.
Recovering expert fees from the other side
Whether you can recover the cost of an expert depends on the court track and the outcome:
- Small claims track (most claims up to £10,000): the expert fees one party can be ordered to pay the other are capped at £750 per expert (Practice Direction 27A, paragraph 7.3). The court must also give permission for expert evidence.
- Fast track and intermediate track: recoverable costs are largely governed by the fixed recoverable costs rules, and the court controls which experts are allowed and for which issues.
- Multi-track: the court can limit the amount of an expert's fees that a party may recover (CPR 35.4(4)), and costs budgets will include expert fees.
Your solicitor will advise on recoverability in your case.
Keeping expert costs proportionate
- Define the questions. A clear letter of instruction listing the specific questions saves time and money.
- Send organised documents with an index, rather than a box of unsorted papers.
- Start with a short preliminary view. It often shows whether a claim is worth pursuing before a full report is commissioned.
- Consider a single joint expert for lower-value technical issues.
- Agree what can be agreed. Early discussion between experts can narrow the issues and sometimes settle the case.
Talk to us about a matter
Baker Accordia provides expert witness services on construction quantum, defects and remedial costs, and surveyor negligence. We give a written estimate for each stage once we have seen the key documents. Contact us for an initial conversation.
This article is general information, not legal advice.
This article is general information for professionals and the public, not legal or professional advice, and does not create a client relationship. The law and procedure described are those of England and Wales as understood at the date of publication. Take advice on your own facts before acting.
Discuss an instruction in confidence.